Question: When looking at the critical path for a delayed project and the project manager sees that adding resources will reduce or remove the delay, the

When looking at the critical path for a delayed project and the project manager sees that adding resources will reduce or remove the delay, the project manager knows that the project is:
Ahead of schedule.
Over Allocated.
Unstable.
Time-Constrained.
Institutipnally Challenged.