Question: QUESTION 4 When looking at the critical path for a delayed project and the project manager sees that adding resources will reduce or remove the

QUESTION 4
When looking at the critical path for a delayed project and the project manager sees that adding resources will reduce or remove the delay, the project manager knows that the project is
Institutionally Challenged.
Ahead of schedule.
lime-Constrained
Over Allocated