Question: When multiple Scrum Teams work together on the same product they have: Multiple Sprint Backlogs that all need to have the same length and need

When multiple Scrum Teams work together on the same product they have:
Multiple Sprint Backlogs that all need to have the same length and need to finish simultaneously
Multiple Sprint Backlogs and corresponding multiple Product Backlogs
Single Sprint Backlog and single Product Backlog
Multiple Sprint Backlogs but single Product Backlog
 When multiple Scrum Teams work together on the same product they