Question: When performing the CPM forward pass, the Early Start is the minimum Early Finish of all immediate predecessors for non - starting activities. Group of
When performing the CPM forward pass, the Early Start is the minimum Early Finish of all immediate predecessors for nonstarting activities.
Group of answer choices
True
False