Question: In making a forward pass through a network, activities L, M, and P are immediate predecessors for activity T, which has an activity time of

In making a forward pass through a network, activities L, M, and P are immediate predecessors for activity T, which has an activity time of 9. The early start times for activities L, M, and P are 22, 17, and 27, respectively. The early finish times for activities L, M, and P are 29, 27, and 33, respectively. What is the early finish time for activity T?

Group of answer choices

29

38

42

33

36

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!