Question: In making a forward pass through a network, activities L, M, and P are immediate predecessors for activity T, which has an activity time of

In making a forward pass through a network, activities L, M, and P are immediate predecessors for activity T, which has an activity time of 13. The early start times for activities L, M, and P are 22, 17, and 27, respectively. The early finish times for activities L, M, and P are 29, 27, and 33, respectively. What is the early finish time for activity T?

Group of answer choices

38

46

44

40

42