Question: When project managers know an activity's _ _ _ _ _ _ _ _ , they are able to compare which critical activities to shorten.

When project managers know an activity's ________, they are able to compare which critical activities to shorten.
Multiple Choice
resources
duration
slope or crash cost per unit
importance
customer-perceived value