Question: When project managers know an activity's ________, they are able to compare which critical activities to shorten. Multiple Choice importance resources duration customer-perceived value slope

When project managers know an activity's ________, they are able to compare which critical activities to shorten. Multiple Choice importance resources duration customer-perceived value slope or crash cost per unit