Question: When scheduling multiple jobs on one machine, which priority rule one should use in order to minimize the average flow time? A. Earliest due date
When scheduling multiple jobs on one machine, which priority rule one should use in order to minimize the average flow time?
| A. | Earliest due date first rule | |
| B. | First-come-first-serve rule | |
| C. | Least slack time remaining rule | |
| D. | Shortest processing time rule | |
| E. | Johnson's rule |