Question: When should a process for handling change requests be defined for a project? During monitoring and controlling During execution During planning During initiating =========================================== What

When should a process for handling change requests be defined for a project?

During monitoring and controlling During execution During planning During initiating

===========================================

What is the main value of the Manage Quality process?

Guides the project manager on how quality will be managed throughout the project

Determines if project outputs do what they were intended to do

Verifies that project deliverables meet stakeholders requirements

Helps the team identify causes of poor quality