Question: When should a process for handling change requests be defined for a project? During monitoring and controlling During execution During planning During initiating =========================================== What
When should a process for handling change requests be defined for a project?
During monitoring and controlling During execution During planning During initiating
===========================================
What is the main value of the Manage Quality process?
Guides the project manager on how quality will be managed throughout the project
Determines if project outputs do what they were intended to do
Verifies that project deliverables meet stakeholders requirements
Helps the team identify causes of poor quality