Question: When the production is low or the sample size is very low, which control chart is preferable? Question 1 2 Answer a . X -
When the production is low or the sample size is very low, which control chart is preferable?
Question Answer
a
X s chart
b
ZMR chart
c
IMR chart
d
X R chart
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock