Question: When there is a contractual requirement for an integrated Program Management Report (IPMR), it is submitted: A. No later than 12 Working days after the
When there is a contractual requirement for an integrated Program Management Report (IPMR), it is submitted:
A. No later than 12 Working days after the end of the contractor's previous accounting period with no exceptions.
B. No later than 12 working days after the end of each month.
C. No later than 12 working days (negotiable up to 17 working days) after the end of the contractor's previous accounting period.
D. The IPMR Data Item Description (DID) provides no guidelines on when the IPMR must be submitted.