Question: When updating a schedule for progress, which is the least important for achieving an accurate forecast of final completion? Establishing a data date Estimating individual
- When updating a schedule for progress, which is the least important for achieving an accurate forecast of final completion?
- Establishing a data date
- Estimating individual activity remaining duration based on trends observed
- Inputting as-built logic changes into the schedule model
- Updating the schedule model to account for changes to means & methods of work remaining to be accomplished
- When reporting progress to upper level management, how can a schedule organized based on the projects WBS be useful?
- Schedule can be converted from ADM to PDM
- Schedule can be manipulated to hide negative aspects
- Schedule can only be crashed if organized by WBS
- Schedule can be summarized to intermediate levels of detail
- In a lump sum contract, all risk is assigned to the following stakeholder:
- Owner
- Contractor
- Architect/Engineer
- All the above
- What is the difference between the end product units and the capacity factor methods of conceptual estimating? What information do you need to perform a conceptual estimate using both of these methods?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock