Question: When using PERT, the critical path must contain enough activities to apply central limit theorem. How many random distribution data should there be? a. More
When using PERT, the critical path must contain enough activities to apply central limit theorem. How many random distribution data should there be?
| a. | More than 5 activities in the path | |
| b. | More than 10 activities in the path | |
| c. | More than 30 activities in the path | |
| d. | More than 20 activities in the path | |
| e. | More than 1 activities in the path |