Question: When using the critical ratio ( CR ) to develop a sequence, Part 2 A . a CR of 1 . 0 means that the

When using the critical ratio(CR) to develop a sequence,
Part 2
A.
a CR of 1.0 means that the job must be scheduled last.
B.
a CR greater than 1.0 means that the job has some slack.
C.
a CR less than 1.0 means that the job is ahead of schedule.
D.
a CR of 1.0 means that the job must be scheduled first.