Question: K When using the critical ratio (CR) to develop a sequence, A. a CR of 1.0 means that the job must be scheduled first. B.

K When using the critical ratio (CR) to develop a sequence, A. a CR of 1.0 means that the job must be scheduled first. B. a CR less than 1.0 means that the job is ahead of schedule. C. a CR of 1.0 mea