Question: When work packages have significant uncertainty associated with the time or cost to complete, we use Question 4Answer a. Phase Estimating b. Bottom-up approach c.

When work packages have significant uncertainty associated with the time or cost to complete, we use

Question 4Answer

a.

Phase Estimating

b.

Bottom-up approach

c.

Top-down approach

d.

Range estimating