Question: When would the project management plan be updated? Whenever there are changes to constraints such as budget, schedule, and regulatory requirements Only at the end
When would the project management plan be updated?
Whenever there are changes to constraintssuch as budget, schedule, and regulatory requirements
Only at the end of the projectto say if the projects goals and objectives were met
Neverthe project management plan is approved and finalized at the beginning of the project
Only when the project breaks groundto update project stakeholders on any design changes
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
