Question: When would the project management plan be updated? Never the project management plan is approved and finalized at the beginning of the project Whenever there
When would the project management plan be updated?
Neverthe project management plan is approved and finalized at the beginning of the project
Whenever there are changes to constraintssuch as budget, schedule, and regulatory requirements
Only at the end of the projectto say if the projects goals and objectives were met
Only when the project breaks groundto update project stakeholders on any design changes