Question: When you appoint a specific resource to a specific task, you create: a. an assignment . b. a cost schedule. c. a project schedule. d.

When you appoint a specific resource to a specific task, you create:

a. an assignment.

b. a cost schedule.

c. a project schedule.

d. a stakeholder.