Question: When you appoint a specific resource to a specific task, you create: a. an assignment . b. a cost schedule. c. a project schedule. d.
When you appoint a specific resource to a specific task, you create:
| a. an assignment.
| ||
| b. a cost schedule.
| ||
| c. a project schedule.
| ||
| d. a stakeholder. |