Question: When you have Cost resources, and resources assigned to a task: The cost is automatically tracked when the task is complete Project gives you the

When you have Cost resources, and resources assigned to a task:
The cost is automatically tracked when the task is complete
Project gives you the option to track these costs automatically or manually