Question: Li is preparing the project schedule for a new project. She is in the process of identifying the amount of time required to a complete
Li is preparing the project schedule for a new project. She is in the process of identifying the amount of time required to a complete a particular task. Which of the following is a more accurate indication of the work effort? Select the best answer.
Question options:
the difference between the start and finish dates
the number of units assigned to the task
the number of hours required to complete the task
the elapsed time
the amount of effortdriven time
Question point
Listen
Which of the following best describes elapsed time? Select the best answer.
Question options:
The level of effort it takes to complete a task
The total calendar time to complete a task
The amount of work periods to complete a task
None of the above
Both a and b they are the same
Question point
Listen
You have met with your project team and determined your project resources. In which view do first begin to enter the information? Select the best answer.
Question options:
Resource sheet
Resource usage
Gantt Chart
Split view
Question point
Listen
For which of the following is a cost not entered when initially setting up the resources in MS Project for a project to build a house?
Question options:
The number of kilograms of cement needed for the foundation
The cost for the general contractor
The costs of the inspection and permits
The hourly rate for electrician and plumber
The overtime rate for the general contractor
Question point
Listen
Pinnacle Event Management has been hired to host a day event project The event will include food and beverages and require a staff of chef, servers and bartenders. Each day the event will start at :PM and will finish at :PM including time for setup and cleanup What are the total Material Costs for this project? Select the best answer:
Chef
$ per hour
Server
$ per hour
Bartender
$ per hour
Venue and Alcohol Permits
$
Dishes, Glasses & Cutlery
$ per person, guests in total
Food & Beverages
$ per person, guests in total
Question options:
$
$
$
$
$
Question point
Listen
Pinnacle Event Management has been hired to host a day event project The event will include food and beverages and require a staff of chef, servers and bartenders. Each day the event will start at :PM and will finish at :PM including time for setup and cleanup What are the total Fixed Costs for this project? Select the best answer:
Chef
$ per hour
Server
$ per hour
Bartender
$ per hour
Venue and Alcohol Permits
$
Dishes, Glasses & Cutlery
$ per person, guests in total
Food & Beverages
$ per person, guests in total
Question options:
$
$
$
$
$
Question point
Listen
You've hired a firm to renovate a bathroom. The project is expected to be completed over days with the work taking place between : AM to : PM each day. The table below lists the various costs for the bathroom renovation. What are the Total Labour costs?
Electrical Inspection & Permits
$
Plumbing Inspection & Permits
$
General Contractor
$ per hour
Plumber
$ per hour
Electrician
$ per hour
Electrical Wiring
$
Plumbing Supplies
$
Lighting and Plumbing Fixtures
$
Question options:
$
$
$
$
$
Question point
Listen
You are in the planning phase of a project. You initially had thought that a task was going to take hours of work time to complete but you now believe it will take hours of work time. Even though there is more work involved in the task you still need it done in one day duration Assuming that you are using a standard calendar for the project hour work day what will the units for the resource in # above show after you have changed the work from to hours? Select the best answer.
Question options:
It will remain at because there are only hours in a work day
It will increase to because the extra hours are more than hours
It will increase to because the resource will need to work more hours to complete the task
None of the above
Question point
Listen
You are in the implementation phase of a project. The person assigned to a task lets you know that she can only work half a day the next day rather than the full day you had initially assigned to the project. This is not a critical task so you are prepared to allow her to reduce the number of hours per day she works on the task. MS Project then generates the following action buttons. Which should you choose in this scenario? Select the best answer.
Question options:
Change the duration but keep the amount of work the same
Change the amount of work but keep the duration the same
Increase the work but keep the hours resources work per day units the same
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock