Question: Which estimating technique uses a statistical relationship to calculate cost or duration based on historical data and other project parameters? a . parametric estimating b

Which estimating technique uses a statistical relationship to calculate cost or duration based on historical data and other project parameters?
a. parametric estimating
b. analogous estimating
c. grass roots estimating
d. empirical estimating