Question: Which estimating technique uses a statistical relationship to calculate cost or duration based on historical data and other project parameters? Question 29Select one: a. empirical

Which estimating technique uses a statistical relationship to calculate cost or duration based on historical data and other project parameters? Question 29Select one: a. empirical estimating b. parametric estimating c. grass roots estimating d. analogous estimating