Question: Which estimation technique starts with estimating durations of lower - level work packages and then aggregates them to estimate higher - level activities?Select one:A .
Which estimation technique starts with estimating durations of lowerlevel work packages and then aggregates them to estimate higherlevel activities?Select one:ATriangular Distribution TechniqueB.Parametric EstimationC.TopDown EstimationD.Parametric EstimationE.BottomUp Estimation