Question: Which is NOT correct about work package? It is the lowest level of the WBS . It is a short - duration task that has
Which is NOT correct about work package?
It is the lowest level of the WBS
It is a shortduration task that has a definite start and stop point, consumes resources, and represents cost.
It should be as dependent of other work packages of the project as possible.
It is the basic unit used for planning, scheduling, and controlling the project.