Question: Which is NOT correct about work package? It is the lowest level of the WBS . It should be as dependent of other work packages
Which is NOT correct about work package?
It is the lowest level of the WBS
It should be as dependent of other work packages of the project as possible.
It is a shortduration task that has a definite start and stop point, consumes resources, and represents cost.
It is the basic unit used for planning, scheduling, and controlling the project.