Question: Which is one objective of Critical Path Method (CPM)?Define the possible activity paths in the project.Determine the amount of scheduling flexibility.Identify the resources needed in
Which is one objective of Critical Path Method (CPM)?Define the possible activity paths in the project.Determine the amount of scheduling flexibility.Identify the resources needed in critical activities.Identify the most important activities, for example, director meetings.