Question: Which is the best reason for why the Project Manager should consult stakeholders before finalizing project planning? To identify where there are activities that may

Which is the best reason for why the Project Manager should consult stakeholders before finalizing project planning? To identify where there are activities that may be deleted or absorbed into other deliverables To confirm the project's critical path To confirm project requirements To develop a preliminary cost estimation benchmark