Question: Which is true of earned value? a . It is the actual cost plus the planned cost. b . It is based solely on the
Which is true of earned value?
a
It is the actual cost plus the planned cost.
b
It is based solely on the total cost estimate to be spent on an activity.
c
It is an estimate of the value of the physical work actually completed.
d
It is also known as the planned value.