Question: Which items below are true about resource smoothing ? (select 3) It will very likely elongate the project duration It will very likely elongate the
Which items below are true about resource smoothing?
(select 3)
It will very likely elongate the project duration
It will very likely elongate the critical path
It will not elongate the project duration
It will not change the length of the critical path
It will even out the resources within constraints
It will resolve all resource over allocations
Question 2
Which items below are true about resource leveling?
(select 3)
It will very likely elongate the project duration
It will very likely change the length of the critical path
It will not elongate the project duration
It will not change the length of the critical path
It will attempt to even out the resources within constraints
It will resolve all resource over allocations
Step by Step Solution