Question: Which job shop scheduling method will the manager choose if his goal is to minimize work - in - process inventory? First - come, first
Which job shop scheduling method will the manager choose if his goal is to minimize workinprocess inventory?
Firstcome, firstserved FCFS
Earliest due date EDD
Shortest processing time SPT
level scheduling