Question: which output from the engineering and manufacturing development phase is established after a positive critical design review that ensures adequate testing has been conducted to

which output from the engineering and manufacturing development phase is established after a positive critical design review that ensures adequate testing has been conducted to prove the system design is stable? a. Initial product baseline b. Test and Evaluation Master Plan c. Acquisition decision memorandum