Question: Which PM application is used when there is uncertainty in task times? Select one: a. Time/Cost analysis b. Multiple Time Estimates c. Crashing d. Normality
Which PM application is used when there is uncertainty in task times?
Select one:
a. Time/Cost analysis
b. Multiple Time Estimates
c. Crashing
d. Normality