Question: Which project schedule compression concept suggests that the project manager should look for opportunities to start selected activites in parallel, even though other activities may
Which project schedule compression concept suggests that the project manager should look for opportunities to start selected activites in parallel, even though other activities may not yet be fully planned?
Fast tracking
Scope reduction
Quality reduction
Grashing