Question: Which Resource is the bottleneck? What is it's Implied Utilization? Given a bottleneck utilization of 112% (assume changes were made since question 1), determine the

Which Resource is the bottleneck? What is it's Implied Utilization?

Given a bottleneck utilization of 112% (assume changes were made since question 1), determine the Actual Flow Rate for all 3 Products A, B, C. What is the sum total demand of the 3 Products?

Given a bottleneck utilization of 132% (assume more changes since question 2), determine the average daily profit for all three products if the profit per each product is:

A: $11.10

B: $ 7.20

C: $ 5.40

(Your number should look like this: 432.10 for $432.10)