Question: Which risk-response option would best describe when a project manager can hire an expert to review technical plans or cost estimates on a project in
Which risk-response option would best describe when a project manager can hire an expert to review technical plans or cost estimates on a project in order to increase confidence in that plan. Risk acceptance Risk avoidance O Risk mitigation Risk monitoring Risk transfer