Question: Which statement about the critical path is not true? A project can have multiple critical path. The critical path determines the earliest time the project

Which statement about the critical path is not

Which statement about the critical path is not true? A project can have multiple critical path. The critical path determines the earliest time the project can be finished. The critical path is the shortest path. Tasks on the critical path have no slack time