Question: Which statement is true about the process steps used to build a project schedule? Sequencing that was performed during work breakdown structure creation is revised

Which statement is true about the process steps used to build a project schedule?
Sequencing that was performed during work breakdown structure creation is revised during scheduling.
Dependencies are determined after sequencing is complete.
Failure to agree on a duration estimate may indicate a need for further task division.
Standards are used to estimate resources, so personnel assignments can be done later.