Question: Which statement is true about the process steps used to build a project schedule? Standards are used to estimate resources, so personnel assignments can be
Which statement is true about the process steps used to build a project schedule?
Standards are used to estimate resources, so personnel assignments can be done later.
Sequencing that was performed during work breakdown structure creation is revised during scheduling.
Failure to agree on a duration estimate may indicate a need for further task division.
Dependencies are determined after sequencing is complete.