Question: Which statement is true regarding a management reserve? they are part of the budget, but not included in the cost baseline the money is used

Which statement is true regarding a management reserve?
they are part of the budget, but not included in the cost baseline
the money is used to cover known risks
the project manager is in control of the management reserve
None of the above