Question: Which variable below is NOT used to estimate task duration? Question 3 1 options: 1 ) duration 2 ) total amount of work, as in
Which variable below is NOT used to estimate task duration?
Question options:
duration
total amount of work, as in person hoursdays that will be done on the task by a resource
consumption of the resource as measured by the threepoint technique
the percent per day of an individuals time that the resource can devote to working on it