Question: Which variable below is NOT used to estimate task duration? Question 3 1 options: 1 ) duration 2 ) total amount of work, as in

Which variable below is NOT used to estimate task duration?
Question 31 options:
1)
duration
2)
total amount of work, as in person hours/days, that will be done on the task by a resource
3)
consumption of the resource as measured by the three-point technique
4)
the percent per day of an individuals time that the resource can devote to working on it