Question: While co mpleting an MRP record, you find that, in Week 4, the gross requirement is 45, and projected available balance for Week 3 is
While completing an MRP record, you find that, in Week 4, the gross requirement is 45, and projected available balance for Week 3 is 20. Lot size is 50, lead time is 1 week. Which of the following will you enter in the planned order release row?
Group of answer choices
25 in week 4
25 in week 3
50 in week 3
50 in week 3, 25 in week 4
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
