Question: While co mpleting an MRP record, you find that, in Week 4, the gross requirement is 45, and projected available balance for Week 3 is

While completing an MRP record, you find that, in Week 4, the gross requirement is 45, and projected available balance for Week 3 is 20. Lot size is 50, lead time is 1 week. Which of the following will you enter in the planned order release row?

Group of answer choices

25 in week 4

25 in week 3

50 in week 3

50 in week 3, 25 in week 4

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!