Question: While completing an MRP record, you find that, in Week 4, the gross requirement is 45, and projected available balance for Week 3 is 20.

While completing an MRP record, you find that, in Week 4, the gross requirement is 45, and projected available balance for Week 3 is 20. Lot size is 50, lead time is 1 week. Which of the following will you will enter in the planned order release row?

Group of answer choices

50 in week 3

25 in week 4

50 in week 3, 25 in week 4

25 in week 3

50 in week 4