Question: While completing an MRP record, you find that, in Week 4, the gross requirement is 45, and projected available balance for Week 3 is 20.
While completing an MRP record, you find that, in Week 4, the gross requirement is 45, and projected available balance for Week 3 is 20. Lot size is 50, lead time is 1 week. Which of the following will you will enter in the planned order release row?
Group of answer choices
50 in week 3
25 in week 4
50 in week 3, 25 in week 4
25 in week 3
50 in week 4