Question: While doing risk response planning, your project team decides to add additional work to the project to help prevent future risks. What document should you
While doing risk response planning, your project team decides to add additional work to the project to help prevent future risks. What document should you immediately update in this scenario? a)Resource Breakdown Structure b) Work Breakdown Structure c) Project Charter d) Risk Probability and Impact Matrix