Question: While performing a backward pass calculation for a network, when multiple paths converge into a predecessor activity, the value carried backward to the late finish

While performing a backward pass calculation for a network, when multiple paths converge into a predecessor activity, the value carried backward to the late finish of the predecessor activity is
Question 23 options:
The smallest late start of the predecessor's immediate successors
The largest late start of the predecessor's immediate successors
The largest early start of the predecessor's immediate successors
The smallest early start of the predecessor's immediate successors

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!