Question: While performing a backward pass calculation for a network, when multiple paths converge into a predecessor activity, the value carried backward to the late finish
While performing a backward pass calculation for a network, when multiple paths converge into a predecessor activity, the value carried backward to the late finish of the predecessor activity is
Question options:
The smallest late start of the predecessor's immediate successors
The largest late start of the predecessor's immediate successors
The largest early start of the predecessor's immediate successors
The smallest early start of the predecessor's immediate successors