Question: While pricing the preliminaries, a contractor determines that they will require the use of a mobile crane for 1 4 working days. The contractor secures

While pricing the preliminaries, a contractor determines that they will require the use of a mobile crane for 14 working days. The contractor secures quotes from the only two plant suppliers in the area and compares them to determine which will be more cost effective.
Supplier 1 charges a flat rate of R10,000 for the hiring of the crane and an additional R2,500 per day for the continued use of the crane. A full day is required for each establishment and disestablishment of the crane.
Supplier 2 charges a rate of R3,500 per day for the hiring of a mobile crane that does not need to be assembled or disassembled.
Which of these suppliers should the contractor choose?
Question 2Select one:
a.
Supplier 1
b.
Supplier 2

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!