Question: While pricing the preliminaries, a contractor determines that they will require the use of a mobile crane for 1 4 working days. The contractor secures
While pricing the preliminaries, a contractor determines that they will require the use of a mobile crane for working days. The contractor secures quotes from the only two plant suppliers in the area and compares them to determine which will be more cost effective.
Supplier charges a flat rate of R for the hiring of the crane and an additional R per day for the continued use of the crane. A full day is required for each establishment and disestablishment of the crane.
Supplier charges a rate of R per day for the hiring of a mobile crane that does not need to be assembled or disassembled.
Which of these suppliers should the contractor choose?
Question Select one:
a
Supplier
b
Supplier
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock