Question: While working with your team members on activity sequencing, a team member identifies that even though a series of activities are planned to be completed
While working with your team members on activity sequencing, a team member identifies that even though a series of activities are planned to be completed in a specific sequence, they can be performed in parallel. What type of activity sequencing method may be utilized in this situation?
Critical path
Resource leveling method
Monte Carlo simulation
Precedence Diagramming Method (PDM