Question: While working with your team members on activity sequencing, a team member identifies that even though a series of activities are planned to be completed
While working with your team members on activity sequencing, a team member identifies that even though a series of activities are planned to be completed in a specific sequence, they can be performed in parallel. What type of activity sequencing method may be utilized in this situation?
A. Critical path
B. Resource leveling method
C. Monte Carlo simulation
D. Precedence Diagramming Method (PDM)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts