Question: Why is it important for the Master Production Schedule ( MPS ) to extend beyond the lead time for producing an item? Why is it
Why is it important for the Master Production Schedule MPS to extend beyond the lead time for producing an item?
Why is it important for the Master Production Schedule MPS to extend beyond the lead time for producing an item?
To enable daily operational adjustments to match shortterm demand changes.
To provide senior management with a clear view of immediate production priorities without considering longterm strategic goals.
To ensure there is sufficient time to acquire materials and labor, and adjust capacity to meet production targets.
To allow flexibility in case customer orders fluctuate significantly.